Shimano, Malaysia
PROJECT TYPE
Warehouse
APPLICATION
Seamless floor on pile
PARTNERS
Owner: Shimano Components (M) Sdn Bhd
General contractor: Bai Lee Sdn Bhd
Flooring contractor: Prima Espirit Sdn Bhd
Engineering office: WDC Sdn Bhd
Downloads
Documents
close
What we do

A faster and cheaper concrete reinforcement solution for Shimano

Shimano Components (M) Sdn Bhd required a new 4,500 m² warehouse extension near their existing factory. The floor needed to meet FM2 category standards due to high racking over 10 meters tall. Bekaert was engaged to provide a solution that ensured flatness and adhered to a tight schedule.

The challenge

 

The main challenges included the contractor’s unfamiliarity with flat floor requirements and the need to achieve the desired level of flatness within a tight timeline.

Shimano Warehouse

The solution

 

Bekaert introduced a flooring partner for the project and proposed using Dramix® 4D combi design (fibers & rebar). This solution offered the contractor and flooring specialist more flexibility in casting the floor and eliminated the cost of armored joints. Additionally, the Dramix® combi design significantly reduced the time and labor required to lay mesh/rebar.

 

As a result, the project was completed successfully. The owner and design engineer were pleased with the seamless floor, which eliminated long-term maintenance issues at the joints. 