Tiong Nam Logistic, Malaysia
PROJECT TYPE
Warehouse
APPLICATION
Jointless floor on piles
PARTNERS
Owner: Tiong Nam Logistic Solution Sdn Bhd
General contractor: JIT Premier Construction Sdn Bhd
Flooring contractor: GC In-house team
Engineering office: Perunding YAA
Downloads
Documents
close
What we do

Dramix® 5D used for reinforced Concrete in warehouse

Tiong Nam Logistic Solution Sdn Bhd, a leading logistics provider, aimed to expand its operations across the country. Their project involved constructing an 18,000 m² warehouse floor, where efficiency and timely completion were crucial.

The challenge

 

The construction project faced significant delays due to a shortage of specialized building materials and issues with subcontractor labor, causing the project to be more than two months behind schedule. To overcome these setbacks and expedite the construction process, the client decided to use steel fiber-reinforced concrete for the warehouse floor.

Tiong Nam Logistic

The solution

 

Dramix® steel fiber reinforcement was integral in creating a jointless floor on piles. The solution utilized the 5D 65/60BG product, demonstrating Dramix®’s versatility for various construction needs. A dosage of 30kg/m³ was applied, enhancing the flooring system’s durability.

 

We collaborated closely with the project’s design engineer, appointed by the developer, to create an alternative design using Dramix® steel fibers. They also provided technical support during the construction phase to address unforeseen on-site challenges. 