Tiong Nam Logistic Solution Sdn Bhd, a leading logistics provider, aimed to expand its operations across the country. Their project involved constructing an 18,000 m² warehouse floor, where efficiency and timely completion were crucial.
The construction project faced significant delays due to a shortage of specialized building materials and issues with subcontractor labor, causing the project to be more than two months behind schedule. To overcome these setbacks and expedite the construction process, the client decided to use steel fiber-reinforced concrete for the warehouse floor.
Dramix® steel fiber reinforcement was integral in creating a jointless floor on piles. The solution utilized the 5D 65/60BG product, demonstrating Dramix®’s versatility for various construction needs. A dosage of 30kg/m³ was applied, enhancing the flooring system’s durability.
We collaborated closely with the project’s design engineer, appointed by the developer, to create an alternative design using Dramix® steel fibers. They also provided technical support during the construction phase to address unforeseen on-site challenges.