Emerald Tycoon Warehouse
PROJECT TYPE
Warehouse
APPLICATION
Seamless slab on piles/Saw-cut floor
PARTNERS
Owner: Sunway
General contractor: Double Success Construction Sdn Bhd
Flooring contr.: Zacklim SRQ Floor Sdn Bhd
Engin. office: Perunding Prima Reka Sdn Bhd
Downloads
Documents
close
What we do

Download

Please provide the following details :

This field is required

This field is required

Please enter valid email (e.g. johnsmith@domain.com)

Efficient Construction with Dramix® at Emerald Tycoon Warehouse 

Sunway, a major developer, is constructing a 20,000 m² warehouse named Emerald Tycoon Warehouse at Sunway Emerald Park in Sepang, Malaysia. The project, which began in July 2024, will feature various racking systems, including AS/RS, and will be equipped with the latest storage and material-handling systems.

The challenge

 

General contractor is looking to achieve cost reduction through Value Engineering while simultaneously aiming to shorten the project completion duration. 


The solution

 

The Dramix® solution utilized a Combi design with 4D 8060BGE at 25 kg/m³ and a top mesh for the slab on pile design in both the internal floor and the loading bay. Additionally, 4D 80600BGE at 20 kg/m³ was used for the concrete topping, with saw cuts made at an average span of 12 meters.

 

Dramix® collaborated with the main contractor and flooring applicator to propose an alternative design that optimized floor thickness. Traditionally, a thicker topping layer was required due to rebar and piling. Steel fibers eliminated the need for rebar, allowing a thinner topping layer, simplifying construction, saving costs, and improving the timeline.